Drone Production Scale-Up Checklist
A practical checklist for FPV drone companies preparing for Drone Dominance orders, gauntlet down-selects, pilot builds, or full-rate production. Eleven areas where production readiness is won or lost.
01
BOM & revision control
- Single controlled BOM is the source of truth — no tribal-knowledge builds
- Revision level appears on every drawing, work instruction, and kit list
- Engineering change process defined: who approves, how the line is notified
- Approved component substitutions documented with equivalency rationale
02
Component sourcing & approved vendor rules
- Approved vendor list (AVL) exists and is enforced at purchasing
- Country-of-origin documentation collected for covered components
- NDAA-covered component screening completed (cameras, radios, flight controllers)
- Second sources identified for long-lead and single-source parts
03
Assembly work instructions
- Step-level work instructions with photos for every build station
- Torque specs, adhesive cure times, and solder standards documented
- Operator training matrix tracks who is qualified on which station
- Instructions versioned and synced to BOM revision
04
QC gates & acceptance criteria
- Incoming inspection criteria defined for critical components
- In-process QC checkpoints at high-risk assembly steps
- Final functional test protocol with written accept/reject criteria
- First article inspection process for every new revision
05
Serialized component tracking
- Serial number scheme defined and applied at a fixed build step
- Component lots linked to finished-unit serials
- Firmware version recorded per unit at flash station
- Test results stored against serial number, retrievable on request
06
Packaging & labeling requirements
- Label spec confirmed with customer (format, UID, barcode symbology)
- Manuals, inserts, and accessories on the pack-out checklist
- Battery handling and ESD requirements documented at pack stations
- Case-pack and palletization specs match customer routing requirements
07
Labor model & throughput assumptions
- Takt time per unit validated by time study, not estimate
- Line balanced across stations — no single station starves the line
- Units-per-shift target set with yield assumption stated
- Ramp curve defined: pilot rate → full rate, with dates
08
Rework & failure tracking
- Defect codes defined and logged at every QC gate
- Rework loop routes failed units through re-test, not around it
- Scrap criteria and disposition rules written down
- Weekly pareto review of top defects drives corrective action
09
Inventory staging & line-side replenishment
- Kits staged ahead of the line for at least one shift of production
- Min/max levels set for line-side consumables
- Shortage escalation path defined — who gets called, when
- Cycle count cadence covers high-value components
10
Fulfillment & shipping plan
- Ship-to rules and delivery points confirmed per order type
- Lithium battery shipping compliance verified (UN 3480/3481)
- Serialized pack lists generated for every shipment
- Proof-of-delivery and shipment records retained per program requirements
11
Surge capacity plan
- Trigger thresholds defined: what order size or deadline activates surge
- Labor surge source identified before it's needed
- Fixtures and test stations duplicated or duplicable on short lead
- Supplier surge commitments documented for critical components
Gaps on this list? That's what the readiness review is for.